PROJECT SUMMARY
R Clark Companies combined earthwork and site development with underground infrastructure for Carlisle Construction Materials’ new Sikeston facility. Cut-and-fill earthwork, building pad and pavement base preparation, rail sub-ballast placement, and storm sewer installation demonstrate the ability to coordinate related civil scopes on a manufacturing development.
Our team was subcontracted by Forcum Lannom Contractors for civil services at the new facility.
SCOPE & PROJECT HIGHLIGHTS
- Cut-and-fill earthwork
- Stone base installation for building pads
- Stone base installation for roadways and parking lots
- Sub-ballast placement for the facility railroad
- Site storm sewers
PROJECT HIGHLIGHTS
- 60,000 tons of stone placed
- 500,000 cubic yards of cut-and-fill earthwork
- Installation of 10,500 linear feet of storm sewer
Check out these other jobs we’ve done.
Earthwork & Site Development · Specialty Construction & Logistics · Utilities & Infrastructure
Ford Hickory II Battery Plant
Glendale, KY
Earthwork & Site Development · Specialty Construction & Logistics · Utilities & Infrastructure
Ford Tennessee Truck Center
Stanton, TN